Week 34 (15 Mar - 19 Mar 2010)

Only four days work this week due to the St Patricks day holiday.
Plasterers got on well though and we now have all bedrooms finished, scratch coat on in the main bathroom, ceiling in main bathroom also finished. They have also managed to get the hall and landing completely scratched coated, which was a feat in itself! Mind you they will have to come back next week to finish off (thought I was being too optimistic on last weeks blog!)

Joiner has been back and has now fitted the plasterboard on the sunroom ceiling, garage ceiling and all walls and ceiling in the room above the garage.

I have a site visit arranged on Tuesday morning with the plumbers and bathroom supplier, so hopefully things will now start moving on that front.


SUNROOM WITH PLASTERBOARD FITTED


MAIN BATHROOM - WALLS SCRATCHED & CEILING SKIMMED






LANDING HEADING TOWARDS BATHROOM






GALLERY & LANDING SCRATCHCOAT ON






GARAGE CEILING WITH PLASTERBOARD






ROOM ABOVE GARAGE ALMOST READY FOR PLASTERING






 